Timeline

Capstone Timeline.

Ian Smith

Lisa Ruch

·      End of January – February 7

o   Edit script

o   Release to potential actors

o   Attempt casting

o   Find House

·      February 8 – February 25

o   Finalize casting

o   Find House

o   Rehearse w/ cast

o   Schedule film dates

o   Gather props

·      February 26 – February 28

o   Start filming

o   Transition from Pre-Production to Production

·      March 1 – March 24

o   Complete filming

o   Transition to post-production

·      March 25 – April 12

o   Complete postproduction for April 13 deadline.

·      April 13 – April 24

o   Do additional polishing for presentation

o   Burn dvds for cast for personal portfolios

o   Look into submissions and distributions to film festivals