Irwin Library 3rd Floor Renovation

By , October 20, 2015 7:14 pm

If you’ve visited the 3rd Floor of Irwin Library recently, you’ve probably noticed that two quads on the north end of the building have been emptied of book stacks.  The library received capital project funding to renovate the northwest quad for relocation of the Center for Academic Technology (CAT) from the basement of Jordan Hall.  The move is scheduled for the beginning of spring semester.

The Center for Academic Technology provides expertise and leadership in the intersections of technology, teaching, and learning in support of the academic mission of Butler University. CAT employees support faculty and staff through consulting and development opportunities and student academic success through the Information Commons program.  CAT employs thirty Information Commons student associates, offering Butler students work experience in a professional environment.

Computer rendering of four computer workstations at a large table with a blue privacy screen dividing the length of the table.

This rendering shows the Information Commons workstations in the CAT office.

Computer rendering of a demonstration theater with a large monitor and laptop on a cart and semi-circular bench seating, behind which are high counter tops and six stools for additional seating.

The CAT office will include a demonstration theatre for presentations about and using instructional technologies.

Phase One of the project (currently under way) includes adding electrical and data infrastructure to support the expanded use of technology in this area. Electricians and network technicians will be installing an additional electrical panel, and  Room IL-116 (currently a small individual study room) will be converted into a data closet. This work includes drilling into concrete walls. Library staff will notify the Butler community in advance about anticipated noise levels whenever possible.

Phase Two will include moving furniture out of the two quads in order to paint the walls and to replace the carpet. We anticipate the painting to take place the week of Nov. 16th, with carpet removal and installation to begin on Nov. 23rd.

Phase Three begins after fall semester ends.  Rather than construct walls within the open quads, we will use a modular frame-and-panel system to create an open-plan office, including: a demonstration theatre and a “genius bar” for exploring new instructional technologies; workstations where Information Commons students will work with faculty on projects; an equipment charging and storage area; a “huddle space” for small group meetings and collaboration; and office spaces for CAT employees. This flexible system may be reconfigured depending upon future needs

Concurrently, starting in November the restrooms in the basement and on the 3rd floor of Irwin Library will be closed for renovation. This much-needed update will include new fixtures, stall partitions, ceiling tiles, and more.  Public restrooms will still be available on the 2nd floor of Irwin during November and December.

The northeast quad of Irwin will also be about painted and re-carpeted as part of this project. Study tables and soft seating will be placed in this quad for Spring Semester, pending approval of a capital proposal to install a library instruction room in this space in 2016-17.

For more information about this project, please contact Heather Vaughn at 940-9926.